[sugar] CODE FREEZE COMING!

Morgan Collett morgan.collett
Mon Oct 29 09:21:02 EDT 2007


Jim Gettys wrote:
> During this week, October 26 through November 1:
> 
>         You should be substantially complete with your development at
>         this date (October 26).
>         
>         If you are not:
>         
>         You MUST notify the community of any significant code you expect
>         will change in the next week.
>         
>         To do this, you MUST create a ticket, tagged "killjoy?" in the
>         keywords field. You MUST briefly justify your recommendation.
>         You MUST include the date you expect your change will be
>         available for testing in the "joyride" build.  This date MUST be
>         before November 2.

http://dev.laptop.org/milestone/XM%20-%20killjoy shows Nov 2 as Feature
Freeze, and Nov 16 as Code Freeze.

You've specified a lot of process, assuming the roadmap dates are
authoritative and we aren't in feature freeze yet...

Which dates are correct?

Regards
Morgan